Overnight Road Closures A27 at Clapham

road-closedjpeg

I am writing to advise that A-one+, on behalf of Highways England will be carrying out drainage pipe replacement, clearing of the pipe network, internal patch and pipe lining repairs. The works will include the construction of a new footpath for access to the balancing pond by Clapham Interchange on the A27.

In order to carry out these works as efficiently and as safely as possible, work will be carried out utilising overnight lane and full closures on the main carriageway and Interchange slip roads between 8pm and 6am. The works will be carried out from Monday 18 November 2019 to Friday 20 December 2019 and are weather dependent.  The construction of a footpath to the nearby balancing pond will be carried out off network from Monday 18 November 2019 for the duration of the works. No works will be carried out at the weekend though these maybe considered for contingencies.

Series of full and lane closures

Dates and timings

A27 Lane 1 closures east and west bound between the slips at Clapham Interchange

Monday 25 November 2019 to Friday 20 December 2019

8pm to 6am

Full closure of the A27 eastbound carriageway at Clapham Interchange

Wednesday 11 December 2019 and Thursday 12 December 2019

8pm to 6am

Full eastbound on and off slip closures and lane 1 eastbound closure on the main carriageway at Clapham Interchange.

Monday 2 December 2019 to Wednesday 11 December 2019

8pm to 6am

Full westbound on and off slip closures and lane 1 westbound closure on the main carriageway at Clapham Interchange

Thursday 12 December 2019 to Friday 20 December 2019

8pm to 6am

Access for emergency vehicles will be provided at all times.

Diversions: Clearly signed diversions will be in place during all closures utilising local routes, suitable for all types of vehicles when full closures of the carriageway are in place.

Eastbound Off Slip Closures: Traffic wishing to leave the A27 at Clapham Interchange will be directed to remain on the A27 eastbound to Offington Roundabout where they can turn around back onto the A27 westbound to return to Clapham Interchange.

Eastbound On Slip Closure: Traffic wishing to enter the A27 eastbound will be directed over the A280 overbridge to join the main A27 westbound to Crossbush Roundabout where they can turn around and re-join the A27 eastbound.

Full Eastbound Carriageway Closure: Traffic will be directed to leave the main A27 via the off slip at the Interchange, cross the roundabout to re-join the A27 to continue their journey onwards. 

Westbound Off Slip Closures: Traffic wishing to leave the A27 at Clapham Interchange will be directed to remain on the A27 westbound to Crossbush Roundabout where they can turn around back onto the A27 eastbound to return to Clapham interchange.

Westbound On Slip Closure: Traffic wishing to enter the A27 westbound will be directed over the A280 overbridge to join the main A27 eastbound to Offington Roundabout where they can turn around and re-join the A27 westbound.

If you have any questions or if you’d like to know about the work taking place, please do not hesitate to contact us.

Phone: 01732 446800

Post: 10, Kings Hill Avenue,

Kings Hill,

Kent

ME19 4AR

Email: area4enquiries@aone.uk.com

info@highwaysengland.co.uk

Web: www.highwaysengland.co.uk

 

Although these works have been carefully programmed they are subject to change. If you would like to be kept up to date with any changes to the programme please send your email address to area4enquiries@aone.uk.com